Tunnel of Perthus case study
Heaters and air movers keep an underground tunnel project on
schedule
The challenge to the Customer
A contractor building tunnels on a new motorway was having
problems with a combination of low temperatures and condensation
during the process of painting the tunnel.
Aggreko's Solution
Due to tight timescales, a quick solution was imperative.
Aggreko supplied 4 x 125kW oil-fired heaters, which blew out hot,
dry air, which was circulated inside the tunnel by 8 x 5,000cfm air
movers, all being powered by an Aggreko generator.