Skip to main content
2017Jan-brazil-pulp-paper-industry-day-manufacturing

Quickly adapting power requirement for paper and pulp manufacturing plant

Client: Tempo Paper

Location: Ogun State, Nigeria

Sectors: Manufacturing

The Challenge

Provide reliable, adaptive power and testing

Tempo are a large, paper manufacturing company, based in Nigeria. It already had a large-scale power solution in place, but the 5.6 MW generator was aging and couldn’t give the customer the reliability they need.

Productivity would suffer eventually if an answer couldn’t be found. This was not an option, so Tempo began the process of looking at all the options available.

Project fact file

Existing power solution 5.6 MW
Of testing 1 Week
Gas generated power 4 MW

Testimonial