Client International supermarket chain
Location Madrid, Spain
Sectors Construction
The Challenge
Overcome intermittent power to create optimum environment for food
Construction of a new supermarket warehouse in Madrid was happening quickly, with tight timeframes in place. There were no room for delays.
The building contained ample HVAC equipment to keep the foodstuffs housed within at optimum temperatures. To maintain freshness that their customers demanded required considerable power – and this threatened to delay completion.
Our customer relied on an emergency generator, but this lacked a stabiliser, which resulted in regular failures.
In order to complete the build and gain assurances for the critical HVAC equipment – dependable and adaptable power was necessary.
Project fact file
800 kVA generators
Constant power
Project stayed on schedule
The Solution
Mobile, modular power with built-in redundancy
We have plenty of experience to call upon in the sector – and it allowed our experts to devise the ideal solution for our customer and their targets.
We rapidly installed two of our 800 kVA generators, synchronising them so they produced the optimal level of power at all times.
With the correct power and the ability to depend on that power, our customer could concentrate on the completion of the warehouse, backed by constant power.
The Aggreko Difference
Our fresh approach will keep your project on time
The Impact
Construction completed within deadline, avoiding losses
Our customer met their target thanks to our power. The HVAC was tested successfully too, which meant that the local community could enjoy the freshest produce.
With our equipment providing the right level of power, with built-in redundancies and the reliability the customer required, it resulted in a successful project, and zero losses through lost time.