Client Major Steel Plant

Location Abu Dhabi, UAE

Sectors Manufacturing

The Challenge

Steel Plant needed temporary cooling to continue production

A major steel plant was experiencing problems with their permanent cooling towers. This meant that they had to be shut down for repair and maintenance, which would cause serious delays in their production schedule there-by facing financial loss. 

Project fact file

20 MW

Cooling provided

2000 m3/h

Flow rate

50 ºC

Water cooled down

The Solution

Aggreko provided cooling in phases as per the plants shutdown schedule

Our specialist temperature control team designed and developed a reliable, cost effective cooling solution capable of delivering 20 MW of cooling tower package in phases. Aggreko team installed two 10 MW cooling tower packages complete with ancillaries at different time schedules to fulfill the changing requirements of the maintenance and repair schedule of the plant

the aggreko difference

Our specialist engineers are experts in developing unique solutions to help you

Our Difference

The Impact

Plant operations continue effortlessly

Aggreko’s unique solution of providing cooling in different phases enabled the customer to overcome the problem and provided the necessary cooling of process water from 58ºC to 50ºC allowing them to continue the production without any stop to the plant