Location Russia
Sectors Oil and gas
THE CHALLENGE
Generate additional power from petroleum gas
Sorovskoye is an oil and gas field located in Salym, in the Tyumen Region of Khanty -Mansiysk
Autonomous District, in Russia - an area with no available power grid connection. Burneftegaz Ltd. (an affiliate of PJSOC Bashneft) started drilling and commissioning new oil wells and so required additional power for oil production and transfer pumps.
Having large volumes of associated petroleum gas (APG), it seemed obvious that the most viable solution was to generate additional electrical power from gas generators.
Aggreko Eurasia won the tender to supply gas generators and transformers to produce 5.5 MW of electricity with an additional capacity for a further 12 MW.
Project fact file
Petroleum gas utilisation rate
Rise in oil production
Total power capacity
THE SOLUTION
50 days to install and
commission
Aggreko provided a turn-key solution, implementing everything - from providing the foundations for the gas generator plant and transformers, to installation and commissioning of the fully functional power plant.
The work included construction of the gas pipeline from the feed source up to the power plant and the internal site gas supply network and cable tray system installation, as well as arranging the warehouse for supplies, oil and lubricants.
The supply pack included six gas generator sets, one transformer, one gas separation and control unit, and sanitary and welfare containers.
Aggreko took just 50 days from putting up the first pole to the power site commissioning, which took Aggreko’s skilled engineering team only three days.
The Aggreko Difference
Expertise and cutting edge technology combined
The Impact
Experience and
expertise deliver to
tight time frames
Aggreko wasted no time and configured the most efficient configuration of equipment, so commissioning could adhere to strict timelines. This included the full range of construction and installation works.
Our experience in APG operations made a massive difference. We were operating 10 similar APG-powered sites at the same time, with a capacity of 70 MW, so our knowledge could make operations faster and more efficient.
“Aggreko promptly mobilised and
deployed a power plant with total
capacity of 12 MW at Sorovskoye
oil field. This enabled us to
compensate a power deficit and
execute our oil production plan in
2015 (which was 171% higher than
in 2014) and ensure associated
petroleum gas utilization of more
than 95%”.
How can we help you?
Get in touch and we’ll help find what’s right for you