Client Myanmar Electric Power Enterprise (MEPE)
Location Myingyan district, Myanmar
Sectors Utilities
The challenge
A dry season alternative to hydropower
Myanmar is changing fast, and relies on constant and reliable power to fuel development. But with 70 per cent of the country’s electricity coming from hydropower and a dry season that lasts from October to May, this was a problem. The Myanmar Electric Power Enterprise (MEPE) started to look for a partner who could install and run an interim power station during the dry months and beyond. After a competitive bid, they asked us to work with them to bring uninterrupted power to the Myingyan district.
Project fact file
Myanmar energy from hydropower
Interim power needed urgently
To deliver the project
Of the workforce from Myanmar
The solution
An interim power plant in 120 days
The challenges here were enormous. The sheer scale of the project meant we needed to source equipment by land, sea and air from 12 different locations around the world. Then our logistics team had to clear it through customs, and bring it through difficult terrain to the site on time. We then installed 92 generators along with transformers, gas-insulated switchgear and a 6 km long 132 kV transmission line connected to the incoming switch bay at the Myingyan substation. Finally, using local natural gas from the China-Myanmar pipeline, we worked with MEPE to set up a high-pressure reduction system, to capture and convert the gas into an efficient fuel source.
the aggreko difference
Investing in local communities, upholding global standards.
The impact
Year-round power and a legacy of a local, skilled workforce
The entire project took only 120 days from start to finish, a huge achievement for MEPE and our power plant team. But supplying critical power was just one of our goals in Myanmar. MEPE also needed to work with a partner who would hire locally, train staff and make sure the plant created jobs and opportunities in the local community. This is something we’re known for wherever we are, and at the Myingyansite, 77 per cent of the workforce are now from Myanmar – which means that the plant is powering the economy in more ways than one.
“We chose Aggreko because of their extensive and proven experience in running large interim power projects, as well as the ability to bring their high standards into a local setting. We are committed to helping local communities benefit from the opportunities presented by the development of infrastructure and with Aggreko this has certainly been possible as 77 per cent of the workforce at the Myingyan temporary power site are Myanmar people.”
How can we help you?
Get in touch and we’ll help find what’s right for you