Data centre keeps its cool

Data centre keeps its cool during upgrade

  • The Challenge

    Keep data centre running optimally during lucrative shopping season

  • The Impact

    Upgrade of facilities, zero downtime, and plenty of happy customers

  • The Solution

    Chillers and cooling towers designed for maximum availability

Client:Data centre

Location:USA

Sectors:Data centres

The Challenge

Data centre can’t afford downtime during shopping season

Black Friday is one of the retail industry’s biggest days. It’s the unofficial start of the Christmas shopping period and Americans, sated from Thanksgiving, go into a retail frenzy. So imagine the headache when a major data centre – which processes millions of retail transactions each day – had to upgrade its cooling system during this time.

Without full data centre availability, retailers wouldn’t be able to process transactions. Every 10 minutes of downtime could mean losses of more than $200 million. Plus, downtime would deliver nationwide notoriety – for all the wrong reasons. The facility needed a temporary system for climate control over the holiday period.

1,600-tonneCooling system
1,000,000+Retail transactions daily
$200 millionPotential loss per 10 mins of downtime

Loading component...

The Solution

Chillers and cooling towers designed for the job

During the upgrade, the facility was facing two weeks without cooling, but we knew just what was needed to cover them during this period. Our engineers and cooling tower specialists teamed up to design a 1,600-tonne temporary cooling system that met needs and also handle increased loads. After all, who knew what Black Friday would bring?

The system combined chillers, cooling towers and generators – plus a standby system in case of failure. It was specially designed to improve cooling water performance and, of course, ensure non-stop availability.

“Aggreko’s industry knowledge, equipment reliability, careful planning and teamwork got a great result for this data centre customer.”

,