A perfectly tailored data centre power plan
A perfectly tailored data centre power plan
Aggreko delivered a customised power solution for a hyperscale data centre in Malaysia, helping the client meet their strict data centre RFS timeline by ensuring reliable power for essential testing during construction.
- The Challenge
Supporting data centre construction
- The Solution
An adaptable power system design
- The Impact
Data centre RFS timeline met with ease
Client:Hyperscale Data Centre
Location:Malaysia
Sectors:Data centres
The Challenge
Supporting data centre construction
As a colocation provider, our customer has to meet stringent timelines to get its new data centre up, running, and providing support for businesses as fast as possible.
The customer had a strict RFS (Ready for Service) timeline – a firm date by which the data centre needed to be operating and meeting performance requirements for service quality.
To meet this deadline, the customer needed to get power online for their data centre as fast as possible, so that they could run the tests needed to prove that the data centre was functioning to a high standard.
The challenge? Any temporary data centre power system design would need to be implemented during construction. Safely running cables and finding space for generators on a construction site would be no mean feat, particularly as plans for the layout of the site continued to evolve.
The customer had a strict RFS (Ready for Service) timeline – a firm date by which the data centre needed to be operating and meeting performance requirements for service quality.
To meet this deadline, the customer needed to get power online for their data centre as fast as possible, so that they could run the tests needed to prove that the data centre was functioning to a high standard.
The challenge? Any temporary data centre power system design would need to be implemented during construction. Safely running cables and finding space for generators on a construction site would be no mean feat, particularly as plans for the layout of the site continued to evolve.
LT & HTCables
8 x 1500kVADiesel gensets
24 x 7On-site operations
20 KLContainerised diesel fuel tanks
22kVTransformers