Testing a data centre's backup power
Testing a data centre's backup power
- THE CHALLENGE
Urgent demand for loadbank testing for diesel generators
- THE SOLUTION
Seamless testing with a phased approach
- THE IMPACT
Delivering results and meeting deadlines
Client:<span style="color: var(--bs-body-color); font-family: var(--bs-body-font-family); font-size: var(--bs-body-font-size); text-align: var(--bs-body-text-align);">Leading data centre provider<br></span><span style="color: var(--bs-body-color); font-family: var(--bs-body-font-family); font-size: var(--bs-body-font-size); text-align: var(--bs-body-text-align);">in the Philippines</span>
Location:Biñan, Philippines
Sectors:Data centres
THE CHALLENGE
Urgent demand for loadbank testing for diesel generators
Our client needed loadbank testing for the commissioning of their backup generators which would be used in a data centre. They were working with a tight time frame to commission the generators on schedule and urgently needed a temporary distribution board solution with associated circuit breakers. As a trusted partner, the client reached out to Aggreko to help meet the demand with a swift temporary solution.
The client needed to test and commission 3 sets of 3 MVA diesel genset units in phase one. Phase two required testing and commissioning of an additional 3 units, adding up to 6 sets of 3 MVA diesel genset units in total.