default

Complete, End-To-End Cooling Saves Time And Cost For Power Plant Project

Complete, end-to-end cooling saves time and cost for power plant project

  • The Challenge

    Rapid cooling for new power plant to avoid costly delays

  • The Solution

    Comprehensive, mobile and precise cooling

  • The Impact

    Costs and delays avoided and project uninterrupted

Client:Established Japanese EPC Contractor

Location:Batang, Central Java, Indonesia

Sectors:Utilities

The challenge

Rapid cooling for new power plant to avoid costly delays

Indonesia’s thirst for power continues to surge as the country undergoes rapid development towards its ambitious economic goals. A Japanese EPC contractor was in the commissioning phase of a 2 GW coal-fired power plant construction project, but the sophisticated cooling system that uses sea and fresh water for the steam turbine ran into issues.

A permanent solution, which requires machinery parts to service the existing cooling system, will take more than six months to deliver as it is custom-made. However, the delivery of the power plant to the Independent Power Producer (IPP) owner cannot sustain delays due to power delivery commitments to the government. Monetary penalties were looming and both the EPC contractor and IPP owner needed to resolve this pressing situation to get the project delivered as scheduled.

2XGT20 Cooling Towers
15monthsRental period
240Condensing water flow rate
32Of cooled water required

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...