After a site assessment undertaken by Aggreko it was then down to our expert engineers and dedicated technical teams to devise the best solution for the mine which would ensure operations could still take place, avoiding no downtime.
The extreme planning involved in this project ensured that everything arrived onto the site on time and made the long journey from Port Sudan into the Nubian desert without any hiccups.
The customer was assured with Aggreko due to an outstanding legacy in the mining sector, which for them, offered a strong competitive solution. The proposal of a flexible rental solution offering both thermal and hybrid power, combined with competitive rates was a no brainer for Manub. Factoring in mining operating experience, know-how and a short mobilisation period made Aggreko a clear first choice.
Due to the scale of the project the delivery was scheduled in two phases. The first phase seeing the installation of 12.5 MW of power and the second would see an additional 14.5 MW of power added to the mine, essentially to keep up with expansion.
Speed was a factor in this project that would make or break it. The strong logistics and project management ensured that from the customer contacting Aggreko, a delivery and install time of just 5 months was all it took.
At the site, the arrival of a complete turnkey solution including 13 diesel generators, was the first phase of the project. The scalable offering ensured that this was the best solution in case energy needs changed over time or needed to be adapted.
A load management system was also in place ensuring that some of the generators would automatically start/stop depending on the load level. Of course, all came with support and maintenance should problems in this volatile environment took place.