Cool Tent Reduces Refinery Risk

Tent cooling system reduce refinery's risks

  • The Challenge

    Eliminate environmental and safety risks for removal of lead-based paint

  • The Solution

    70 tonnes of cooling in a sealed tent

  • The Impact

    Zero safety or environmental reports, cost savings for the customer

Client:Refinery

Location:USA

Sectors:Petrochemical and refining

The challenge

Risk-free conditions for lead paint removal

A major overhaul of a refinery is not an exercise to take lightly. Unexpected delays and safety hazards cost time, money and sometimes lives. Our customer was aiming for an incident-free overhaul, with zero environmental or safety reports. This meant they needed an unpleasant and potentially risky job done before they could even start. They wanted lead-based paint removed from one of their larger vessels so they could complete a welding project. 

Others had tried dealing with this problem in the past but with only minimal success. The refinery asked if we could do a better job, and do it during normal operational hours.

150Vessel surface temperature
90°F-85°FWorking temperature maintained
0Safety and environmental incidents

Loading component...

Loading component...

“Our customer was so impressed they turned to us for solutions again and again."

,