When extreme heat strikes, modular cooling keeps production on track
Client: Major EPC Contractor - North Field Expansion Project
Location: Ras Laffan, Qatar
Sectors: Oil and Gas
The Challenge
Sweltering conditions risked worker safety and critical project delays
While critical for worker safety, these measures significantly restricted working hours and slowed down progress on the North Field Expansion Project. Already facing delays due to supply chain hurdles, the client urgently required cooling solutions in key operational areas, including pipe racks, confined tanks, and the production facilities, to maintain productivity and avoid further slippage in the timeline.
The project also posed installation challenges due to tight spaces and layout restrictions, particularly in confined zones, where fewer units could be deployed despite higher cooling demands.
Fact File
The Solution
Quickly deployed cooling to keep work safe and continuous
Aggreko conducted an in-depth site assessment and designed a tailored cooling solution that accounted for harsh ambient conditions of DB 48°C / WB 34°C and logistical constraints.
The HSE-compliant solution provided cooling for critical infrastructure, including pipe racks, storage tanks, and the production facility, ensuring continuous workflow.
Aggreko mobilised quickly, integrating equipment into the site with minimal disruption and while navigating space restrictions in confined and open zones. The system was fully compliant with safety regulations and supported by a 24/7 operations team handling everything from preventive maintenance to real-time cooling adjustments. Aggreko ensured that the project stayed on schedule, no matter what.
The Impact
Cooling that kept construction safe and moving
With round-the-clock support, Aggreko ensured fleet uptime was maximised safely and effectively, keeping the North Field Expansion Project moving forward.