Offshore Platform Gas Turbine Overcapacity And Inefficiency Solved

Offshore platform Gas Turbine overcapacity and inefficiency solved

  • The Challenge

    Inefficiency and lower oil prices lead to overcapacity of an existing gas turbine

  • The Solution

    Providing back-up power for remaining gas turbine with our gas generators using available APG

  • The Impact

    Higher efficiency, lower costs

Client:Dana Petroleum

Location:Netherlands

Sectors:Oil and Gas

The challenge

Inefficiency and lower oil prices lead to overcapacity of an existing gas turbine

With two oversized Gas Turbine main engines of 4.3 MW in total power each and the evident consequences of lower oil prices, our customer’s offshore platform power was highly inefficient.

One of the existing gas turbines had a considerably low efficiency of just 14%. With low oil prices also impacting activity levels, the platform was unable to use all of the 4.3 MW that was generated. The overcapacity was increasingly costly and with our customer facing considerable cost pressures, they needed a temporary solution fast.

2 1.1 MWGas generators on APG
5yearsContract duration
1mSaving on maintenance costs