Client Myanmar Electric Power Enterprise (MEPE)

Location Myingyan district, Myanmar

Sectors Utilities

 
The challenge

A dry season alternative to hydropower

Myanmar is changing fast, and relies on constant and reliable power to fuel development. But with 70 per cent of the country’s electricity coming from hydropower and a dry season that lasts from October to May, this was a problem. The Myanmar Electric Power Enterprise (MEPE) started to look for a partner who could install and run an interim power station during the dry months and beyond. After a competitive bid, they asked us to work with them to bring uninterrupted power to the Myingyan district.

 

Project fact file

70 %

Myanmar energy from hydropower

95 MW

Interim power needed urgently

120 days

To deliver the project

77 %

Of the workforce from Myanmar

 
The solution

An interim power plant in 120 days

The challenges here were enormous. The sheer scale of the project meant we needed to source equipment by land, sea and air from 12 different locations around the world. Then our logistics team had to clear it through customs, and bring it through difficult terrain to the site on time. We then installed 92 generators along with transformers, gas-insulated switchgear and a 6 km long 132 kV transmission line connected to the incoming switch bay at the Myingyan substation. Finally, using local natural gas from the China-Myanmar pipeline, we worked with MEPE to set up a high-pressure reduction system, to capture and convert the gas into an efficient fuel source. 

 

the aggreko difference

Investing in local communities, upholding global standards.

 
The impact

Year-round power and a legacy of a local, skilled workforce 

The entire project took only 120 days from start to finish, a huge achievement for MEPE and our power plant team. But supplying critical power was just one of our goals in Myanmar. MEPE also needed to work with a partner who would hire locally, train staff and make sure the plant created jobs and opportunities in the local community. This is something we’re known for wherever we are, and at the Myingyansite, 77 per cent of the workforce are now from Myanmar – which means that the plant is powering the economy in more ways than one.

 

“We chose Aggreko because of their extensive and proven experience in running large interim power projects, as well as the ability to bring their high standards into a local setting. We are committed to helping local communities benefit from the opportunities presented by the development of infrastructure and with Aggreko this has certainly been possible as 77 per cent of the workforce at the Myingyan temporary power site are Myanmar people.”

U Htein Lwin Managing Director ,
Myanmar Electrical Power Enterprise

How can we help you?

Get in touch and we’ll help find what’s right for you