NFE project power case study 2

Reliable modular power solutions for extreme environmental challenges

Reliable modular power solutions for extreme environmental challenges

  • The Challenge

    Supporting pre-commissioning operations with reliable modular power

  • The Impact

    Timely and reliable power delivery under extreme conditions

  • The Solution

    Tailored on-demand power systems for seamless integration

Client:Major EPC Contractor - North Field Expansion Project

Location:Ras Laffan, Qatar

Sectors:Oil and Gas

The Challenge

Supporting pre-commissioning operations with reliable modular power
The North Field Expansion Project required immediate, stable power to support the pre-commissioning and commissioning of critical systems including HP pumps, motors, and utility/process infrastructure. With the permanent grid connection still unavailable, any delay in power availability risked impacting the project timeline.

Adding to the complexity, the work had to be completed during the summer months under tough ambient conditions, and while maintaining strict HSE compliance. Aggreko stepped in as a partner that could deliver a safe, reliable, and fast-tracked solution.
SafetyStrict HSE maintained
24/7Team support on-site
17.4Total power supplied

Loading component...

The Solution

Tailored on-demand power systems for seamless integration

Aggreko worked closely with the client’s project team to assess site-specific power requirements and deliver a fit-for-purpose high-voltage solution, broken down as follows:

  • 7.2 MW-11 KV high-voltage power for the desalination plant
  • 7.2 MW 6.6 KV high-voltage power for the process area
  • 3 MW 6.6 KV high-voltage power for utility systems

The solution was devised to meet specific load profiles and operational requirements, including design validation, engineering support, and layout planning. A certified HV engineer oversaw the entire operation, ensuring complete safety and compliance. Aggreko also provided 24/7 support, covering both preventative and reactive maintenance throughout the duration of the project.