Contingency plan for when the unthinkable happens

Contingency plan for when the unthinkable happens

  • The Challenge

    Being prepared for a plant failure in a data centre

  • The Solution

    Robust contingency plan to ensure business as usual

  • The Impact

    Ready-to-go plan saves the day when needed

Client:Data centre facilities management company

Location:Surrey, UK

Sectors:Facilities management

THE CHALLENGE

Being prepared for a plant failure in a data centre

Data centres need constant power and cooling to function. Any type of plant failure can cause untold problems for the facilities management companies that run them.

Fact File

1Robust contingency plan
3 x 200 kWChillers installed
2 x 500 kVAGenerators to provide power
Download case study
Hero image for water-cooled Chillers landing page mobile

THE SOLUTION

Robust contingency plan to ensure business as usual

Our design engineers designed a bespoke plan for each site. So when hot weather strained the chiller plant at one of the data centres, its plan was quickly put into action.

Following a call on Friday evening we delivered, installed and commissioned three 200 kW chillers, a 1 MW heat exchanger and two 500 kVA generators - plus all the relevant hoses, cables, and fuel tanks.

We then plugged it all into the site’s chiller plant to support it with supplementary cooling to meet the requirements until the seasonal spike in temperature subsided.

THE IMPACT

Ready-to-go plan saves the day when needed

Everything was ready to go, so when the temperature rose and the cooling plant couldn’t cope, no one needed to get hot under the collar.

The facilities manager made the call and we got straight to work activating according to the plan. This saved considerable time, as everything was already in place - site surveys, installation plan, and who was responsible for what.

Everybody knew just what to do, and it was done quickly and efficiently, just as we’d planned.