Ensuring Swift Data Centre Equipment Delivery During Covid-19

Ensuring swift data centre equipment delivery during Covid-19

  • The Challenge

    Supply chain disruptions due to Covid-19, meaning equipment delivery delays for the customer

  • The Solution

    Responsive Turnkey L1 Factory acceptance test pushing logistics ahead and saving time

  • The Impact

    Reputation safeguarding for the customer during a period of intensifying competition

Client:Leading UPS OEM

Location:Philippines

Sectors:Data centres

The Challenge

Supply chain disruptions due to Covid-19, meaning equipment delivery delays for the customer

One of the world’s leading Uninterrupted Power Supply (UPS) Original Equipment Manufacturer (OEM), was due to deliver a 400 kVA UPS for its Data Centre (DC) customer in the Philippines. The DC was due to receive the UPS in a week’s time for its expanded facility.

Covid-19 meant that the traditional route of delivery for the customer would be delayed due to issues in the supply chain with various lockdowns. With a looming delivery deadline of just a week, the UPS units had to arrive from the Philippines - then be tested and commissioned in order to be accepted by the DC at its facility.

The customer would traditionally partner with local vendors for testing needs, but with time against them on the occasion, a quick response turnaround with seamless project execution had to take place – there was no room for error or further delays.

With our strong reputation for delivery on short notice and deep experience in DC-specific turnkey load-testing solutions, the OEM customer turned to Aggreko to meet the tight deadline and meet their rigorous technical inspection standards.

2daysof rigorous testing
2 400 kWload banks
2Power Generators
1 400 kVAUPS unit underwent rigorous testing