Powering an LNG mega project’s construction phase
Powering an LNG mega project’s construction phase
- THE CHALLENGE
Power to remote location until at least 2024
- THE SOLUTION
Flexible power and local workforce training
- THE IMPACT
Domestic and worldwide LNG from local staff
Client:Global EPC Joint Venture
Location:Mozambique, Africa
Sectors:Oil and Gas
THE CHALLENGE
Power to remote location until at least 2024
This EPC Joint Venture required power for the construction phase of their customer’s $20 billion onshore LNG facility project. The facility is situated in an extremely remote coastal area of Mozambique - 450km from the nearest city, Pemba.
With no grid power available, they needed Aggreko to provide power for the construction phase, beginning in June 2024. To ensure we understood the full complexity of the task in hand, we engaged with the Joint Venture early in the process and advised them on each phase of the project and associated requirement.
Both partners of the JV had worked with Aggreko before and were confident of our expertise and track record in support O&G project as well as local knowledge of this region.
Aggreko’s local subsidiary in Mozambique have delivered over 200MW of power since establishing in 2012 and was a key differentiator in been awarded this mega project.
Initially, 32MW was required for the main power plant and 5 standalone gensets were needed for remote construction areas.
The power capacity was adjusted upwards following a change in the project timescales to 36MW reflecting the extra power needed for the camp contractors which would reach a peak of approximately 18,000.