THE CHALLENGE

Energy for remote worker housing

This oil and gas customer needed a way to provide off-grid energy to a housing camp for its workers, keeping them safe and comfortable while on site.

Their existing MTU generators provided 2 MW of capacity at medium voltage, but they needed another 4 MW to cover all their electricity needs.

This created an extra hurdle, as the additional generators had to synchronise with their existing ones, despite having a different rating, controller, and voltage output.

Compounding the challenge, the site was located in a remote area, in the hottest part of Saudi Arabia.

Fact File

4{2DC79272-84A9-42C6-B29F-3276C50C2478}Power supplied
6 PackGenerator configuration
13.8{38B31EE5-EE8B-4434-9DD5-C4341BB61DD2}Setup voltage requirement