Enabling first-of-its-kind CDU commissioning in India through load testing

India's first Coolant Distribution Unit (CDU) commissioning solution in Bengaluru for a data centre project. Aggreko developed an innovative liquid cooling solution deploying a 600 kW electrical boiler and rigorously managing the entire seven-day testing program under strict cleanliness protocols. 

Client
Lab Testing Facility
Location
Bengaluru, India
Sector
Data centres
  • THE CHALLENGE

    Supporting a first-of-its-kind CDU testing application in India

  • THE SOLUTION

    Liquid cooling testing engineered around precision

  • THE IMPACT

    Providing the conditions required for critical CDU testing

THE CHALLENGE

How Aggreko supported a first-of-its-kind CDU testing application in India

A major data centre project in Bangalore required testing of a Coolant Distribution Unit (CDU) before package start-up. The customer needed to test the CDU as part of a critical programme for its end client, but faced a significant technical challenge: the CDU could not be operated without a suitable load source.

The testing process required a carefully engineered solution capable of supporting the CDU while maintaining strict operating parameters throughout the programme.

Adding further complexity, this represented the first known CDU testing application of its kind in India. The CDU operated using PG25% coolant on the secondary circuit and was highly sensitive to contamination. Any foreign particles introduced during testing could affect the integrity of the system, making cleanliness and control critical requirements throughout the project.

The customer needed more than equipment. They needed a partner capable of designing and managing a controlled testing environment built around the CDU's specific operating requirements. To support the programme, Aggreko collected and analysed key operating data, including temperature profiles, flow rates and pressure requirements, before developing a tailored testing solution.

800 kW TOTAL CDU CAPACITY
450 kW DESIGNED TESTING LOAD
50 % TESTING CRITERIA
600 kW ELECTRICAL BOILER

Loading component...

THE SOLUTION

Liquid cooling testing engineered around precision

Aggreko worked closely with the customer to understand the CDU's operating requirements and develop a bespoke liquid cooling load testing solution tailored to the application.

Our team gathered and analysed key operating parameters across both primary and secondary circuits, enabling the design of a testing package aligned to the customer's specific requirements.

The data centre commissiong solution included a 600 kW electrical boiler and all associated equipment required to support the testing programme, delivered and managed as a complete package by Aggreko.

The system was engineered around the customer's testing criteria, including:

  • 800 kw: total CDU capacity
  • 450 kw: designed testing load
  • 50%: testing criteria
  • 100%: water primary circuit
  • PG25: secondary circuit

The package was designed around the following operating parameters:

 20°C ± 3%

 Primary inlet temperature

  33°C ± 3%

 Secondary inlet temperature

 28.8°C ± 3%

 Primary outlet temperature

 24.6°C ± 3%

 Secondary outlet temperature  

Because of the sensitivity of the CDU, Aggreko implemented strict handling and cleanliness procedures throughout deployment and operation to minimise contamination risk.

Two Aggreko specialists managed the testing programme on site, overseeing installation and operational support throughout the seven-day project.

This was not simply an equipment deployment. It was an engineered testing solution designed around accuracy, control and the customer's specific technical requirements.

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...