Offshore Industry oil and gas production petroleum pipeline.

Accelerating decommissioning during oil price slump

Accelerating decommissioning during oil price slump

  • The Challenge

    Decommissioning of an offshore oil field, northeast of Aberdeen, was due to begin in 2021

  • The Solution

    Speedy turnaround including virtual Factory Acceptance Testing

  • The Impact

    Losses due to drop in oil price minimised by bringing project forward by 1 year

Client:International Oil Company (IOC)

Location:North Sea

Sectors:Oil and Gas

The Challenge

Decommissioning of an offshore oil field, northeast of Aberdeen, was due to begin in 2021

However, when low oil prices and the Covid-19 pandemic hit, The IOC wanted to bring forward the plans by a year to save money. Due to the short notice, they needed a power provider who could move fast - the tender was issued in April 2021, awarded in July, and had to be installed just four weeks later in August.

They required complete power to the platform, including accommodation, crane and seawater pumps. As the project was High Voltage (H.V.), they also required a partner with H.V. capability.

Factory Acceptance Testing also had to be carried out on the generators at the height of the pandemic when the movement of staff and equipment was severely restricted.

3 x 1500 kVAGenerators to power platform
5 yearsDecommissioning project duration
4 weeksTo install complete power solutions