Working alongside our local partner, Shanduka, we pinpointed the ideal place to start – an unused gas concession, with an existing off-take point in the main pipeline in Ressano Garcia. We’d take gas from here, and build and run an interim gas-fuelled power plant feeding directly into the SAPP network. Electricidade de Mozambique (EDM) and South Africa’s Eskom were both interested in buying the extra power, and with natural gas from the Matola Gas Company SA, and a sub-concession agreement with Gigawatt Mozambique SA, we began to work together on this hugely ambitious project.
In just 20 weeks, we built a fully functioning 100 MW power plant, with EDM taking 18 MW and Eskom 92 MW. Once the plant was running, Namibian state utility provider NamPower bought into the project, and we increased the plant capacity by another 122 MW to 232 MW in total.