1285 AGG ME NESMA Aramco CS_Banner_LND

$name

Delivering reliable off-grid energy in challenging conditions

Sectors:Oil and Gas

THE CHALLENGE

Energy for remote worker housing

This oil and gas customer needed a way to provide off-grid energy to a housing camp for its workers, keeping them safe and comfortable while on site.

Their existing MTU generators provided 2 MW of capacity at medium voltage, but they needed another 4 MW to cover all their electricity needs.

This created an extra hurdle, as the additional generators had to synchronise with their existing ones, despite having a different rating, controller, and voltage output.

Compounding the challenge, the site was located in a remote area, in the hottest part of Saudi Arabia.

Fact File

4MWPower supplied
6 PackGenerator configuration
13.8kVASetup voltage requirement
1285 AGG ME NESMA Aramco CS_Banner_SQU

1285 AGG ME NESMA Aramco Case Study-2
Tags
  • Case Study
  • Middle East
  • Oil and Gas