Powering a hydro dam build
Powering a massive hydro dam construction
- The Challenge
Power construction and workers’ accommodation in a remote part of Canada
- The Solution
Tailored package with load-sharing to reduce outages
- The Impact
Minimal production downtime, compliant with EH&S regulations
Client:Manitoba Hydro – Keeyask Project
Location:Manitoba, Canada
Sectors:Utilities
The Challenge
Powering a remote dam construction project
Up in the wilderness of Manitoba, an ambitious project was underway to build the first of three hydroelectric dams that would supply power to utilities in both Canada and the US.
First, the utility needed the installation, supply and delivery of prime power for the workers’ accommodation and the construction sites. That’s a lot of temporary power. And given that all activities, from construction to cooking, relied on that power there was no room for outages. It had to be consistent, it had to be reliable and it had to be mobile.