Client: Pharmaceutical fine chemical manufacturer

Location: Ireland

Sectors: Pharmaceuticals

The challenge

Power for pharmaceutical manufacturer limited by grid capacity

Our customer is a leading science & technology company who wanted to expand its manufacturing capabilities in Ireland by building a new manufacturing facility.

However, the Ireland distribution network operator informed our customer during the planning application process that the full mains supply for this new site would be several years away.

This delay in production would lead to hundreds of millions of Euros per annum in lost revenue & profits for the company.

We proposed using our gas generators to supplement the existing supply, giving them the flexibility to scale up or down depending on the site’s needs over the coming years.

Key facts

MWA scalable set-up 1.4 - 6.3
project duration 3 - 5 years
power supply gas generator 1.4 MWe

The solution

1.4 MW electricity powered from onsite gas to address grid

constraints

Very early on in the project discussions, Aggreko assembled a professional major projects team to instil confidence in all parties involved in the project. Virtual meetings took place every week over an 18-month period to move this project from opportunity to order. We assured the factory that choosing Aggreko means there would be no delays in their project milestones. Our bridging gap power solution incorporated:

  •  1 x gas generator 1.43 MWe
  • 1 x 6.3 MVA 415/20kV transformer
  • Gas pressure control skid
  • Sound attenuation panel system
  • LV cabling

The impact

Gain time and production using temporary power solution

We ensured the customer could proceed with their project timelines & milestones, without any worry that the facility will be completed without mains power going into production. This allowed them to pre-sell & build their sales pipeline, with certainty, before a single unit comes off the production line.

We offered a scalable solution, depending on the site’s power needs over the next 3-5 years. There are no upfront Capex needs for this project, the entire cost could be funded through Opex funding. Aggreko look after all maintenance & service needs for the duration of the hire.

In the rare case of malfunction, we can simply replace the unit with another from fleet. This gives the customer piece of mind, that there would be no major disruption in their production schedules.