When a private hospital's operating theatre air conditioning malfunctioned on a Friday night, requiring the temperature to be maintained below 20°C for critical surgeries, Aggreko rapidly deployed two FC50 chillers. These were installed and operational within 36 hours, ensuring that scheduled life-saving procedures could proceed without delay.
Client:Private Hospital
Location:Mornington, Australia
Sectors:Facilities management
The Challenge
To quickly cool and maintain temperature of an operating theatre
Late night on a Friday is not the best time to have your air conditioning malfunction. Especially when it's in a hospital that relies on optimised temperatures to perform life-saving surgery.
With the failure of the operating theatre's chiller, our Aggreko solution was required to maintain the theatre temperature below 20C - ASAP. The hospital didn't just need urgent temperature control - delays could have life-changing consequences.
Loading component...
The Solution
Two FC50 chillers installed and running within 36 hours
Time was the most valuable commodity here, every second counted. How quickly could we regulate the temperature of the operating theatre and allow the hospital staff to do their work?
Our ability to respond rapidly was put to the test, but Aggreko are the world leaders in temporary power and temperature control for a reason. From the moment the hospital called us on Friday night, we had our reliable, mobile and modular equipment up and running in just 36 hours.
We achieved such a quick response by working together with our customer and by using our extensive experience in such critical circumstances.