Client Resolute Mining Limited (Resolute)

Location Mali, Africa

Sectors Mining

THE CHALLENGE

World leading technology to deliver cost effective power that ultimately lowers gold production costs

Resolute Mining Limited, an ASX and LSE listed gold mining company has produced over eight million ounces of gold from 10 gold mines.

As part of its commitment to delivering a life-of-mine allin sustaining cost of US$746/oz at its Syama Underground Mine in Mali, they needed to define a lower cost power solution relative to its existing source of power.

The Syama Gold Mine is currently powered by singular diesel generators that were no longer the most efficient compared to newer technology now available. At the mercy of diesel, notoriously a fluctuating high cost fuel, it has become an expensive solution. Furthermore, the generators had to run constantly to provide system stability that the mine needed.

After investigating the possibility of a grid connection, which was disregarded on the basis of time and cost, Resolute launched a tender with the target of achieving a 40% reduction in the cost of electricity (COE). With Resolute focused on securing a more environmentally friendly solution, the environmental impact of the power solution being offered was a key consideration.

Resolute also wanted a solution which offered low cost power without needing to make a significant upfront capital investment so that the Company could conserve capital for deployment for growth.

With many possible options, Resolute needed a trusted power advisor

Project fact file

40 %

Cost reduction in COE

20 %

Reduction in CO2 emissions

1st

Wärtsilä Modular Block Project

THE SOLUTION

A 16-year contract to build, operate and maintain a hybrid power plant (thermal, solar, batteries)

As Aggreko had been providing and operating a 28 MW diesel power plant on the site that augments the existing diesel power station for a few years, we had both the reputation and credibility to step in and offer support.

A vast project needed a vast solution and we relished the opportunity to work with Resolute to deliver a bespoke cutting edge technical and commercial solution as part of a 16-year Power Supply Agreement (PSA).

Technical offering

Delivered in two stages, it considers the various project factors with a meticulous level of detail to ensure smooth delivery and zero disruption to the mine’s production activity.

Stage one is expected to be completed in 2020 and will comprise of three 10 MW thermal Wärtsilä Modular Block’s and a 10 MW battery storage system, that will provide spinning reserve displacement and outbalance sudden jumps in load.

The second stage will consist of the installation of an additional 10 MW Wärtsilä Modular Block in 2022 and the addition of 20 MW solar PV power in 2023.

There can be some hesitancy to implement solar as mine’s have short planning horizon’s and the usual lifespan of a PV park is about 20 years - if not sometimes longer than the operation of a mine itself. This is why the offering Aggreko provides perfectly matches a mine’s needs.

The initial site infrastructure layout will include space to accommodate a l fifth 10 MW Wärtsilä Modular Block, enabling the mine to add additional power capacity if needed in the future to support growth or expansion plans.

Once the solar power system is installed, the 10MW battery storage system will also manage the output of the solar power system, smoothing out fluctuations in PV generation and facilitating integration into the hybrid system.

Commercial Offering

Our pricing was structured with a combination of fixed and variable charges depending on electricity required, and evolving MW installed. It also includes an incentive programme where Aggreko shares between 25% to 50% of the resulting fuel savings if improved efficiencies for key performances indicators in the contract are achieved. This provides us with an incentive to further reduce the cost of power for Resolute, and we share that cost benefit directly with our customer.

During the project engineering phase we forged a true partnership with Resolute to ensure we use the best site infrastructure, and optimise the civil work and installation of the plant. As an example, the solar array will be constructed on the surface of the existing Syama Tailings Storage Facility (TSF) thereby maximising positive environmental outcomes and augmenting Resolute’s rehabilitation program.

THE AGGREKO DIFFERENCE

Going for gold – a complete hybrid solution

Download case study here

THE IMPACT

$10 million cost savings in the first full year of operation and reduced environmental impact ensuring long term mine sustainability

The power as a service agreement with this hybrid offering allows Resolute to focus on their core business of Mining while delivering substantial cost savings, estimated at 2 million euros per month on their current total cost of energy – that’s a 40% reduction from current COE. These savings will flow directly into Resolute’s production cost per ounce and help them operate in any gold price environment, which is crucial for the long-term sustainability of their mining operations.

Once the Solar power plant is integrated into the mine’s energy mix, Resolute will also improve the mine’s environmental impact with a reduction in carbon emissions of approx. 20%

The ongoing presence of Aggreko at the site, and appetite to adopt a new world leading technology demonstrates the trust and strong partnership in place.