Innovative Solution And Virtual Pipeline Satisfies Peak Demand During Summer

Innovative solution and Virtual Pipeline to meet seasonal peak demand

A 48 MW energy solution combining gas generators and virtual gas pipelines enabled our customer to meet the projected growth in power demand. With adaptable technology and seamless logistics, Aggreko delivered uninterrupted power to 3.3 million residents despite the pandemic and a 100-day natural gas supply disruption.
  • The Challenge

    Bridge projected power deficit and change fuel supply after project installation

  • The Impact

    Successfully meet supply obligations despite pandemic and fuel supply failure predicament

  • The Solution

    48 MW of reliable energy from a conventional and virtual gas pipeline

Client:Energía Solar Cachanilla (ESCO)

Location:Mexicali, Baja California, Mexico

Sectors:Utilities

Loading component...

48MWof power
2 sites4 months contracted
3.3mpeople benefiting