Temporary construction power goes hybrid to save fuel, emissions
Ausco partners with Aggreko to introduce a hybrid energy solution to power construction sites during freeway construction in Melbourne.
Client: Ausco
Location: Melbourne, Australia
Sectors: Construction
The Challenge
Efficient power for freeway construction
During the construction of a freeway, Ausco needed temporary power for facilities such as traffic lights and modular site buildings that were not connected to the grid.
As they were carrying out the construction work in a residential area they also needed to minimise noise as much as possible.
Having worked with Aggreko for a number of years, Ausco asked us to provide a solution that would deliver all the power they needed in the most efficient and environmentally friendly way while ensuring that the construction project could be completed on time.
Project facts
The Solution
Right-sized hybrid power for four constructon sites
These units were sized according to the power needs of each site, with generators ranging from 30 kVA to 125 kVA in capacity and batteries ranging from 30 kVA to 90 kVA.
This allowed Ausco to rely on battery power as much as possible, only using the generators when there was a high power demand or when the batteries needed recharging.
Sales Effectiveness Manager, Ausco Modular
Rachele Jowett
The Impact
Notable fuel savings and reduced CO2 emissions
By quickly installing the generators and batteries at each site we ensured that Ausco had all the power needed to keep the construction of the freeway on track.
Thanks to the batteries, generator use was dramatically reduced, keeping noise to a minimum as well as delivering significant savings in terms of both fuel costs and carbon dioxide emissions.
Across the four sites, Ausco saved a total of 71,236 litres of fuel and produced 190,912 kg fewer CO2 emissions than if the generators had been providing all the power.