Drying out a construction site in winter weather

Client: Ashcourt Group

Location: Durham, England

Sectors: Construction

The Challenge

Fast drying a wet winter building site

A little rain never hurt anyone, but a lot of bad weather can spell time delays and budget blowouts for a construction site. A construction company Ashcourt called us when they found themselves behind schedule on the construction of four student accommodation buildings. The interior had been exposed to the extremes of a British winter causing site workers frustrations and delay.

Key Project Facts

Buildings needed drying and heating 4
Modular mobile heater 125kW
generator used to power the heater 30 kVA
Durham's daily winter sunshine 2 hours
heater 200 kW

The Solution

One modular mobile system for drying four buildings

To dry out the building, we packaged up a 125kW diesel space heater and ducting connected to a 30 kVA generator. This was linked to a 1,000-litre fuel tank to minimise the footprint. Because the equipment was modular and easy to move, we only needed one heater to dry out all four buildings.

“The solution meant we could meet project deadlines ahead of schedule despite the bad weather.”

Project Manager , Ashcourt Group

Matt Tinker

The Impact

Project schedule and winter weather beaten

Despite the bad weather, the project was delivered ahead of schedule. Savings were made by only having to hire one effective modular heater for all four buildings. By rolling the power and temperature control into one package, the customer needed to manage only one supplier, one point of contact and invoice, saving on coordination tasks and administration time.