Skip to main content

Temporary construction power goes hybrid to save fuel, emissions 

Ausco partners with Aggreko to introduce a hybrid energy solution to power construction sites during freeway construction in Melbourne.

Client: Ausco

Location: Melbourne, Australia

Sectors: Construction

The Challenge

Efficient power for freeway construction

During the construction of a freeway, Ausco needed temporary power for facilities such as traffic lights and modular site buildings that were not connected to the grid. 

As they were carrying out the construction work in a residential area they also needed to minimise noise as much as possible. 

Having worked with Aggreko for a number of years, Ausco asked us to provide a solution that would deliver all the power they needed in the most efficient and environmentally friendly way while ensuring that the construction project could be completed on time.

Project facts

30 kVA to 90 kVA 4Batteries
of CO2 saved 190,912kg
30 kVA to 125 kVA 4Generators
of fuel saved 71,236Litres
Melbourne freeway construction

The Solution

Right-sized hybrid power for four constructon sites

We designed a hybrid power system that involved the installation of both diesel generators and battery storage units at four separate locations across the freeway construction area.

 These units were sized according to the power needs of each site, with generators ranging from 30 kVA to 125 kVA in capacity and batteries ranging from 30 kVA to 90 kVA.
 
This allowed Ausco to rely on battery power as much as possible, only using the generators when there was a high power demand or when the batteries needed recharging.
This particular project with the hybrid units gives us the opportunity to model the performance of the product… and take this information to our other customers… and offer them really valuable data and insight in what sort of savings they can achieve on site.

Sales Effectiveness Manager, Ausco Modular

Rachele Jowett

The Impact

Notable fuel savings and reduced CO2 emissions

By quickly installing the generators and batteries at each site we ensured that Ausco had all the power needed to keep the construction of the freeway on track.

Thanks to the batteries, generator use was dramatically reduced, keeping noise to a minimum as well as delivering significant savings in terms of both fuel costs and carbon dioxide emissions.

Across the four sites, Ausco saved a total of 71,236 litres of fuel and produced 190,912 kg fewer CO2 emissions than if the generators had been providing all the power.

Need reliable temporary power for your construction site?

A hybrid power solution from Aggreko will keep your project on track.