2017-02-gold-mine-russia.jpg

Power to expand remote gold mine

Power to expand a remote cold mine

  • The Challenge

    Provide alternative power for a gold mine during the Siberian winters

  • The Impact

    24/7 power with the capacity to control fuel consumption

  • The Solution

    12 MV ready-to-go power package

Client:GV Gold

Location:Irkutsk region, Russia

Sectors:Mining

The Challenge

Alternative power for a gold mine during the bitter Siberian winter

GV Gold, a gold mining operation in the Irkutsk region of Russia was looking to expand by opening a third mine. But getting power to a remote location in Siberia is no walk in the tundra. True, they could get some power from a nearby hydroelectric plant, but during the winter months the dam overflow was increased to prevent the damn from freezing, which meant a lot less hydro-capacity downstream.

PROJECT FACT FILE

12MWTotal power supplied
30 °CSummer temperature
-40 °CWinter temperature
“The quality of the Aggreko equipment along with the excellent service and technical support has proved that Aggreko was the right choice for GV Gold.”

General Director , OJSC Vysochaishy (GV Gold)

Sergey A. Vasiliev

Tags
  • Mining
  • Case Study
  • Diesel generators