Refurbishment power and load testing for five offshore platforms

Client: Oil and Gas Operator

Location: North Sea

Sectors: Oil and Gas

Rich text preheading goes here

Additional power during gas turbine replacement and platform process improvements

Our customer took ownership of an ageing and underperforming oil field which consisted of five offshore platforms. They needed power to facilitate the platform refurbishment which included process improvements and planned / emergency maintenance as well as upgrading the ageing existing gas turbines.

As the gas turbines were the only source of power on the platform, the customer needed a reliable supplementary power supply to full support the platform during this process.

Project fact file

HV DNV Rig safe power packages 2
Loadbank 14 MVA
Service 24 /7
Cleaning a loadbank at Singapore depot

The Solution

Full service DNV rig safe package and load testing

As a full-service power specialist provider, we handled all planning activities which included strategic planning, scope mapping and preproject planning to ensure that the solution was efficient, safe and fit for purpose. The customer took full advantage of our full turn-key service, so our engineers operated and maintained the power package 24/7 for two years. Our support and reliability allowed We needed to provide High Voltage DNV Rig safe packages - not something everyone can do.

The first package consisted to a 2 MVA Low Voltage package’s with a 2.5 MVA High voltage step up transformer at 11 kV. The second package consisted of a 3 MVA low voltage package with a 6 MVA high voltage transformer, also at 11 kV. We also provided a 14 MVA load bank test, to allow final completion and testing of the new gas ring main and turbine installation.

The Impact

Visit us at aggreko.com to get in touch Production uninterrupted and new turbines go live on schedule

The customer took full advantage of our full turn-key service, so our engineers operated and maintained the power package 24/7 for two years. Our support and reliability allowed these works to be undertaken with limited interruption to production, and the load testing ensured the new turbines would go live with impact on the platform.