Eliminating generator power
Refinery executes a flawless turnaround without diesel generators
- The challenge
Status quo
- The impact
Early engagement
- The solution
Use existing ressources
Client:Petroleum Refinery
Location:California
Sectors:Petrochemical and refining
The Challenge
Status quo
The connected load was calculated at 22.8 MVA. Using proprietary monitoring technology and data gathered from past projects, Aggreko quickly determined the load to be excessively large for a project of this size and scope. Following a thorough vetting process, peak demand was dialed back to 10.9 MVA, a 52% reduction in demand, resulting in significant cost savings. While working with the client’s in- house engineering team, multiple 2.4 kW sources were identified, and a feasibility study was performed to determine if available power could be connected in advance without interrupting ongoing production. Aggreko’s electrical engineers proceeded to design a temporary installation using existing house power after the feasibility test declared it was possible.