Temporary steam during onsite steam generator repair
Temporary steam during onsite steam generator repair
- The challenge
Steam for paper manufacturer after generator breakdown
- The solution
13,5 t/h steam generator
- The result
Fulfilling orders thanks to temporary steam
Client:Paper manufacturer
Location:Italy
Sectors:Manufacturing
The challenge
Steam requirement for paper manufacturer after steam generator breakdown
A manufacturer of paper products with various sites in Italy reached out to Aggreko with requirements of a methane boiler, with a steam output of approximately 30 t/h at 8 bar for their Vicenza site.
This production site is very important to the customer because it is one of the only sites that produces skate paper. Unfortunately, their on-site steam generator broke down, pausing the production process of paper-making and any office heating.
Steam is crucial because it is used to heat process equipment, including the drying cylinders of the carton/paper machine. Downtime for the manufacturer could become very costly, so a swift solution was essential.
Loading component...
Loading component...
The result