2017-02-rolling-paper-at-factory.jpg

Temporary steam during onsite steam generator repair

Temporary steam during onsite steam generator repair

Client:Paper manufacturer

Location:Italy

Sectors:Manufacturing

The challenge

Steam requirement for paper manufacturer after steam generator breakdown

A manufacturer of paper products with various sites in Italy reached out to Aggreko with requirements of a methane boiler, with a steam output of approximately 30 t/h at 8 bar for their Vicenza site.

This production site is very important to the customer because it is one of the only sites that produces skate paper. Unfortunately, their on-site steam generator broke down, pausing the production process of paper-making and any office heating.

Steam is crucial because it is used to heat process equipment, including the drying cylinders of the carton/paper machine. Downtime for the manufacturer could become very costly, so a swift solution was essential.

Millions €saved in lost production
90 daysproject duration
13,5 t/Hsteam requirement