Carroll Cotton Company faced losing roughly $100,000 every single day that reliable and stable power was not connected to the new plant. It was set to be a bumper year for the harvest, and it meant every resource would need to be used. That included the new plant. Without it and prospects looked bleak.
Aggreko were contacted to deploy a rapid and proven bridging power solution. One that could keep the new cotton processing plant operational and ensure that the harvest would not go to waste.
Four Aggreko G4 1500 kVA generators and a specialist Low Voltage Switchroom were installed on site, hooked up to a 30,000 litre double bunded fuel tank. This would mean less logistics in the remote region for refuelling, and it would meet site environmental requirements.
The entire plant power solution would be maintained, optimised and supervised by a local team of experts and a 24-hour remote team that could minimise any conceivable obstacle.
It was the perfect contingency for the ideal power supply. And it fit the bill for the Carroll Cotton Company in their time of need.