case study icon

Supporting Data Centre upgrade with greener technology

Supporting Data Centre upgrade with greener technology

  • The challenge

    Provide power for temporary office cabins during build phase

  • The impact

    High performance combined with lower fuel usage and emissions

  • The solution

    Balancing power with efficiency

Client:Data Centre

Location:Denmark

Sectors:Data centres

The challenge

Provide power for temporary office cabins during build phase

Our client was tasked with delivering an essential upgrade to a data centre in Denmark. We were brought onboard to provide 1000 kVa power for temporary on-site office cabins during the build phase.

There were multiple challenges to consider. As site occupancy changed, the load would need to flex. It was agreed that a single solution was required to meet all load needs from start to finish, rather than creating added disruption by changing the system mid-project.

Space and laydown restrictions posed another challenge, meaning the equipment had to fit into a pre-determined bunded area. Time was also of the essence. The power-on date was approaching fast, and the solution needed to be live and commissioned within just 4 weeks.

At a time of high global fuel costs, efficiency and decarbonisation were important considerations.

300kWBattery Energy Storage System (BESS)
3 x 320kVAGenerators
2WeeksTurnaround

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...