Our client was tasked with delivering an essential upgrade to a data centre in Denmark. We were brought onboard to provide 1000 kVa power for temporary on-site office cabins during the build phase.
There were multiple challenges to consider. As site occupancy changed, the load would need to flex. It was agreed that a single solution was required to meet all load needs from start to finish, rather than creating added disruption by changing the system mid-project.
Space and laydown restrictions posed another challenge, meaning the equipment had to fit into a pre-determined bunded area. Time was also of the essence. The power-on date was approaching fast, and the solution needed to be live and commissioned within just 4 weeks.
At a time of high global fuel costs, efficiency and decarbonisation were important considerations.