Full offshore platform commissioning support
Full offshore platform commissioning support
- The challenge
Temporary power and cooling for offshore platform commissioning
- The solution
Complete package to cover all the requirements of the commissioning project
- The impact
Platform commissioned on time with no need for additional suppliers
Client:Multinational oil and gas company
Location:Ingleside, Texas
Sectors:Oil and gas
The Challenge
Temporary power and cooling for offshore platform commissioning
A new offshore platform had been manufactured in Korea and was then sent to Ingleside, Texas to be commissioned before being deployed in the Gulf of Mexico. The operator required a temporary solution for power and cooling for their equipment and staff during the commissioning project until the platform was ready to be deployed at sea. They had a tight deadline they were working to when the platform had to be operational so it was critical that all the necessary commissioning and testing work was completed on time.
Loading component...
Loading component...
The Impact
Platform commissioned on time with no need for additional suppliers
The customer was able to complete all the commissioning and testing in time to get the platform into the Gulf of Mexico and operational on schedule. Partnering with Aggreko meant they could take advantage of our wide range of equipment to cater for all their commissioning needs rather than having to bring in separate suppliers for different aspects of the project.