A trailer-mounted blue Aggreko oil free air compressor at a desert

Pipeline testing support services shorten commissioning process

Pipeline testing support services shorten commissioning process

  • The challenge

    Minimize the time to cool water for oil and gas pipeline hydro-testing

  • The solution

    A cooling system that dropped 50 F out of the hydro test-water in less than 5 hours

  • The impact

    Faster commissioning with reduced associated project crew costs

Client:Pipeline construction company

Location:Texas, USA

Sectors:Oil and gas

The Challenge

Minimizing the time to cool water for hydro-test

Pre-commissioning an oil and gas pipeline for field readiness requires a series of tests to ensure the structural integrity of the piping system before the final product is introduced. Chief among these procedures is the hydrotest, a pipeline flooding and pressurization process whereby water is introduced to test for leaks. Test water temperature must be stabilized and cooled to the pipeline’s organic temperature before the actual pressurization portion of the test can be initiated. The pipeline must then be drained and dried to complete the commissioning process.

One of the biggest challenges for pipeline construction companies is minimizing the time it takes to cool the test water. Hot ambient temperatures can result in water temperatures as high as 43.5 °C, and it can take up to 10 days for this water to stabilize to an acceptable temperature. Time spent waiting for test water to stabilize organically is often unacceptable to operators and their service companies, especially considering the high costs associated with keeping crews on-site.

Such was the case with an Aggreko customer when commissioning 4,600 feet of newly constructed pipeline in Texas. The water was stored on the surface in eight fracturing (frac) tanks, and its temperature needed to be reduced from 43.5 °F to 21 °C before flooding and pressurizing the pipeline. Once the hydrotest was completed, the water needed to be reflowed back into the frac tanks, and the full length of pipeline dried according to stringent moisture specifications.

400 ton chillerFor water cooling
From 43.5°C to 15.5°CIn less than 5 hours
1,500 CFM Diesel ACOil-free air to push the water into the pipeline and then back into the frac tanks
1 MW generatorTo power the water cooling system

Loading component...

Loading component...

The Aggreko team quickly engineered a turn-key solution that drastically accelerated the customer’s timeline for pipeline pre-commissioning.

Aggreko ,

Loading component...

Loading component...

Loading component...

Loading component...