  • The Challenge

    Extra power to meet load demands from largest ore stacker in the world

  • The Impact

    Our power supplied within weeks so mine project stayed on budget

  • The Solution

    Devise rapidly deployed power station to ensure new mine project stayed on track

Client:South Flank Mine

Location:Western Australia

Sectors:Mining

The Challenge

Extra power to meet load demands from largest ore stacker in the world

BHP's US$3.6 billion South Flank iron ore mine under construction in Western Australia is one of the most technologically advanced mine projects in the world. Not only is it projected to deliver around 80 Mt of ore a year, it will harness the latest and greatest innovations in the field to allow the 600 operational staff to ensure productivity.

This will include autonomous-ready haul trucks and the world’s largest rail-mounted stacker.

Fact File Heading

3MWTotal power
30 klSize of fuel tank
33 kvSubstation transformer

Tags
  • Mining
  • Australia Pacific