Major Midstream Company

Permian Basin, Texas, USA

Sectors Oil and gas

The challenge

To decompress and supply 42MW of gas to the grid

When these extremely largescale cryogenics plant asked for our help processing huge gas streams and getting them onto the power grid, we realized this would be our biggest power project yet in North America.

The challenge was threefold. First, we needed to decompress gas that was nearly ten times more compressed than usual. Second, we had to bring emissions in line with West Texas and Federal requirements, and last but not least, we had to incorporate a custom real-time monitoring system.

Project fact file

25 MW

Phase 1

42 MW

Phase 2

5

Cryo Streams

75 %

emissions reduction required

1250 psi

Incoming gas pressure

The solution

A one of a kind design, including comprehensive SCR

Our experts developed a complete skid system to handle the high decompression requirements.

When it came to reducing emissions by 75% percent, we designed and installed custom SCR and oxidation catalyst setups to retrofit on each natural gas generator.

To achieve real-time monitoring capabilities, our local team brought in our overseas SCADA colleagues for additional support and we designed and implemented a world-class monitoring system for maximum uptime. Together, we have provided over 25 natural gas generators during phase one with a plan to have over 40 generators during phase two.

the aggreko difference

Our experts from all over the world contributed to this revolutionary project for North America

The impact

A perfect combination of reliable power and reduced emissions

SCR design allowed customer to obtain air permits quickly, while the mobile gas power system allowed production to begin far ahead of permanent utilities reaching the site.

“You can rely on us to draw up the most effective solution for your business.”