Structure of a large transmission tower against a blue sky.

Helping T&D companies realize capital quicker and expedite grid improvements

Flexible utility power solutions for grid modernization

  • The challenge

    Two Sub-Transmission lines needed pole replacement and re-conductoring without impacting the utility's customers

  • The solution

    Providing temporary power generation to avoid unnecessary grid outages

  • The impact

    Finally closing out a capital project that had been going on for years

Client:A large utility company

Location:USA

Sectors:Utilities

The Challenge

Two Sub-Transmission lines needed pole replacement and re-conductoring without impacting the utility’s customers

The poles in a radial sub- transmission system were at the end of life... and at risk of failure. New poles had been in place for over 5 years; however, they could not be re-conductored without an 8 hour outage.

The utility was looking for a way to complete their capital project while not impacting their customers or their reliability metrics (i.e. SAIDI & SAIFI). When the field operations team heard what Aggreko was for one particular system, they identified another section of the grid that could benefit from the same work. By bundling the jobs back to back, the utility was able to dramatically improve their productivity.

Enabledcapital that had been deferred for 5 years
0interruption to customers
ExpeditedGrid Hardening by 5 years

Loading component...

The Solution

Providing temporary power generation to avoid unnecessary grid outages

The choice was easy for the utility because of Aggreko’s demonstrated success injecting temporary power into the grid with zero customer impact.

Aggreko was able to safely provide temporary generation at 4,800V for both feeders. During the project, Aggreko’s engineering team ensured the system was running flawlessly.

Aggreko maintained communication with the large utility company while mobilizing, testing, running, and demobilizing the equipment.

Clear, concise directions from Aggreko’s project manager helped make the project a success, as most of the utility’s workers had never witnessed temporary generation projects of this nature.

 

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...