Hybrid grid emulation system reduces emissions

Hybrid grid emulation system reduces emissions

  • The challenge

    Mitigating project risks while incorporating BESS

  • The solution

    As a world leader in the energy transition, Enel has centred sustainability as a key aspect of its commissioning projects

  • The impact

    Aggreko’s hybrid approach reduced fuel consumption and cut greenhouse gas emissions by 67%, and resulted in significant cost savings

Client:Enel Green Power

Location:Throckmorton, Texas

Sectors:Utilities

Loading component...

78Wind turbines commissioned
4MWGrid Emulation package
67%Reduction in emissions & fuel consumption