Reducing a utility’s outage time by 99 percent
Reducing a utility’s outage time by 99 percent
- The challenge
Keeping customer lights on during utility upgrades
- The solution
A ready-to-go package with the manpower to support it
- The impact
Reliable power alternatives allowed successful upgrades
Client:Major utility company
Location:Trimble, Ohio, USA
Sectors:Utilities
The Challenge
Keeping customer lights on during utility upgrades
A major electric utility company was conducting upgrades to a transmission line, which would require a two-day outage to complete the work. Unfortunately, this would leave many customers without power for several hours. Immediate on-site power at 13KV was needed to keep the distribution network energized to avoid outages and unhappy customers.
Equipment would need to be deployed and set up within a week, but since hunting season was underway, no access was allowed on the site until two days before the outage was set to occur.