90 MW of scalable mobile power for a Caribbean island
- The Challenge
Provide reliable & efficient power to avoid daily power outages
- The Solution
Scalable power delivered in different stages: 40 MW initially + 40 MW of expansion + 10 MW new contract
- The Impact
We provide approximately 50% of the power supply with higher efficiency generators at a competitive cost
The Challenge
Provide reliable & efficient power to avoid daily power outages
There is a paradise island located in the Caribbean that has beautiful reefs, corals, and clear beaches. This island is a popular destination for cruises and for thousands of tourists throughout the year. The utility company on this island faced various challenges in generating the required power and meeting the demand of its population.
The power generation relied on a very inefficient power generation system, and due to this, there were frequent power outages on a daily basis. This situation caused a great deal of damage to electrical equipment on the island, in addition to affecting the quality of life of its inhabitants and tourists. Furthermore, all of this had a significant impact on the island’s economy.
Key Facts
- 90 MW of supplied energy
- 50% of island’s power
- 92 generators installed in very limited space