Client:General Contractor

Location:Houston, TX

Sectors:Construction

The Challenge

Balancing community concerns with operational efficiency

A Houston construction site located in the middle of a residential area required a reliable and efficient energy solution for its temporary site office for seven months. The general contractor (GC) had initial concerns: noise reduction was crucial to avoid disturbing the nearby residents, and minimizing operational costs was a top priority.

Traditionally, a standard generator could have been used for a project of this scope, but that would mean around-the-clock fuel consumption. Additionally, if the GC decided to cut the generator off after working hours, the temporary site office would face daily limitations such as a lack of food storage and consistent air-conditioning.

The client needed a solution to address noise concerns, reduce fuel consumption, and ultimately lower operational costs.

77%Less CO2 emitted
79% Less fuel intensive
$16,100+Average monthly fuel cost savings