Turning a troubled power project around
Turning a troubled power project around
- The challenge
Powering a factory after a fire
- The solution
A rapid rethink and power deployment
- The impact
Perfect performance and a very happy customer
Client:Property Restoration Contractor
Location:Cleveland, Ohio, USA
Sectors:Construction
The Challenge
Powering a factory after a fire
A long-standing partner of Aggreko, a property restoration company, brought us in to provide temporary power for their customer following a devastating electrical fire. An industrial battery manufacturer was at a complete halt and without power as a result of the fire. Replacing their damaged equipment was going to take months, so they needed a temporary power solution to help them get back up and running. A month into the project it was smooth sailing for our team, but unexpectedly a generator caught fire, triggering a succession of other issues.
The facility had already been down and without production long enough, and we couldn’t allow them to go without power again on our account. We quickly assembled a team to assess the situation and restore power and functionality to the facility.