Rapid cooling and cleaner power for a dairy processing facility
Rapid cooling and cleaner power for a dairy processing facility
- The challenge
A dairy processing plant needed urgent cooling but had no spare power capacity or time for upgrades
- The solution
Production remained online with lower costs, reduced emissions, and no infrastructure changes
- The impact
Aggreko delivered instant cooling with diesel power, then transitioned to cleaner natural gas
Client:A rural dairy processing plant
Location:Ohio
Sectors:Manufacturing
The Challenge
A dairy processing plant needed urgent cooling but had no spare power capacity or time for upgrades
A large dairy processing plant in rural Ohio urgently needed additional process and comfort cooling during peak production. However, the site’s existing electrical infrastructure had no spare capacity to support new chillers, and utility upgrades would take months to complete. The facility required an immediate and reliable solution to deliver the necessary cooling while avoiding costly downtime or permanent modifications. The challenge was to balance short-term production needs with a long-term plan for efficiency and compliance, all without disrupting daily operations.