Power requirement for paper and pulp manufacturing plant
Quickly adapting power requirement for paper and pulp manufacturing plant
- The Challenge
Provide reliable, adaptive power and testing
- The Solution
Optimised and efficient power and rapid deployment
- The Impact
Reduced fuel costs and improved productivity
Client:Tempo Paper
Location:Ogun State, Nigeria
Sectors:Manufacturing
The Challenge
Provide reliable, adaptive power and testing
Tempo are a large, paper manufacturing company, based in Nigeria. It already had a large-scale power solution in place, but the 5.6 MW generator was aging and couldn’t give the customer the reliability they need.
Productivity would suffer eventually if an answer couldn’t be found. This was not an option, so Tempo began the process of looking at all the options available.
Loading component...
The Solution
Optimised and efficient power and rapid deployment
Our blend of sector expertise and mobile, modular equipment made Aggreko the preferred option ahead of the competition.
The 5.6 MW existing generator needed serious maintenance so we deployed 2 MW of thermal generation to ensure a smooth transition and operation.
Our loadbank testing services were also put into play, to ensure that the equipment could handle the potential demand and scope for growth.
The customer soon discovered that the 5.6 MW generator was not a viable option going forward.
Our expertise and swift response had impressed Tempo, so we entered discussions to install 2 MW of gas power on site.
The customer could have the flexibility to ramp up or scale down their power needs with our rentable model – and we did just that by adding a further 2 MW of gas generation.